NOTICE is hereby given under Section 14(2)(a) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers which will close the following length of road to allow contractors to relocate the site welfare facilities from the Sacred Heart School site:
Nature and period of restriction - Road closure
Name of road - Greenside, between Ailsa Street West and Duncan Street.
This Notice commences on 19 April 2022 and has a maximum duration of 5 days or until the works are completed, whichever is sooner. The works are expected to commence from 7:30am on Tuesday 19 April 2022 with completion anticipated by 6:00pm later that same day.
The days and times of the works may be dependent upon the weather conditions but the restriction will be implemented only when the appropriate signs are displayed.
Emergency Services access will not be affected and access for residents, deliveries and pedestrians’ out-with the working zone will be maintained.
Alternative route – Access for residents and deliveries will be maintained whenever possible.
Kevin Braidwood
Head of Roads
Ayrshire Roads Alliance
8 John Finnie Street
Kilmarnock
KA1 1DD
Section 14(2)(a) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers