EAC No. 10412
East Ayrshire Council
( Kennedy Drive, Kilmarnock)
(Temporary Road Closure) Order 2024
On 26th March 2024 the Council, in exercise of the powers conferred on it under Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers, made the above-named Order, to allow works on belhalf of Andrew Strain Construction Ltd
Temporary Road Closure – Kennedy Drive, Kilmarnock - New Farm Loch
From junction Livingstone Court east bound for 190m
The Order commences on 15 April 2024 and has a maximum duration of 18 months or until the works are completed, whichever is earlier. The works are expected to commence from 15 April 2024 at 08:00 until 27 May 2024 at 18:00
The days and times of the works may be dependent upon the weather conditions but the Order will be implemented only when the appropriate signs are displayed.
Emergency Services access and access for residents, deliveries and pedestrians’ out-with the working zone will be maintained via diversion route.
An alternative route will be signed via Kennedy Drive, South Dean Road, B7082 Grassyards Road, Kennedy Drive and vice versa.
Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers