EAC No. 10240
East Ayrshire Council
( Clunch Road, Stewarton)
(Temporary Road Closure) Order 2023
On 12th September 2023 the Council, in exercise of the powers conferred on it under Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers, made the above-named Orderto allow BT Works
Temporary Road Closure – Clunch Road, Stewarton, for 800m
The Order commences on 02 October 2023 and has a maximum duration of 18 months or until the works are completed, whichever is earlier. The works are expected to commence from 02 October 2023 at 08:00 until 13 October 2023 at 17:00
The road is expected to be closed between 08:00 and 17:00 each day with it being open out-with these times.
The days and times of the works may be dependent upon the weather conditions but the Order will be implemented only when the appropriate signs are displayed.
Emergency Services access will not be affected and access for residents, deliveries and pedestrians’ out-with the working zone will be maintained.
An alternative route will be signed via the B769 onto the B778 onto Cutstraw Road back onto Clunch Road and vice versa
Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers