East Ayrshire Council 
( U735,U712,and U732, Mauchline)
(Temporary Road Closure) Order 2023

On 02 May 2023 the Council, in exercise of the powers conferred on it under Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers, made the above-named Order, to allow BT Works 

Temporary Road Closure – U735,U712,and U732, Mauchline, 

The Order commences on 16 May 2023 and has a maximum duration of 18 months or until the works are completed, whichever is earlier. The works are expected to commence from 16 May 2023 at 07:00 with the closure remaining in place until 29 May 2023 at 19:00.

The days and times of the works may be dependent upon the weather conditions but the Order will be implemented only when the appropriate signs are displayed. 

Emergency Services access will not be affected and access for residents, deliveries and pedestrians’ out-with the working zone will be maintained.  

An alternative route will be signed via

  A76 - A70 - B7036 - C50 and U732 for works on U735/U712 and vice versa 

  U712 - A76 - A70 - B7036 and C50 for works on U732 and vice versa 

 

Legislation Information

Section 14(1) of the Road Traffic Regulation Act 1984, as amended, and of all other enabling powers

Attachments: