Balnagask Heating Duct

Location: Balnagask Heating Duct
Restriction Type: Road Closure
From: 19 Apr 2022 06:00
Until: 15 Jul 2022 06:00

Aberdeen City Council has made the above-named order in terms of its powers under Section 14(1) of the Road Traffic Regulation Act 1984

The effect of the order, which will operate from 06:00 on 19 April 2022, until 06:00 on 15 July 2022, is to impose the restrictions listed below. Works will be carried out in phases, and advance warning signs will be on street at least one week before each phase commences.

Phase 1; Prohibition of driving on Greenwell Road, Aberdeen, from the railway underpass at Ladywell Place to Somebody Cares House. There will be a prohibition of waiting on either side of the same stretch of road. An alternative route is available via Hillview Road and Greenbank Road.

Phase 2; From 06:00 on 25 April 2022, until 06:00 on 29 April 2022, a Prohibition of driving on Farquhar Avenue, Aberdeen, from its junction with Farquhar Road to the car park access at numbers 174-190 Balnagask Road. There will be a prohibition of waiting on either side of the same stretch of road. An alternative route is available via Farquhar Road and Balnagask Road.

Phase 3; One-way restriction on Greenwell Road, Aberdeen, from its junction with Greenbank Crescent to the exit from Air Liquide. The permitted direction of travel will be eastbound only. There will be a prohibition of waiting on the same stretch of road. An alternative route is available via Hillview Road and Greenbank Road.

Phase 4; Prohibition of traverse by pedestrians on the footpath at the side of Air Liquide to Steadfast House. An alternative route is available via Greenbank Road, Hillview Road, and Greenwell Road.

Phase 5; From 06:00 on 25 April 2022, until 06:00 on 15 July 2022, a Prohibition of driving on Rockall Road, Aberdeen, from its junction with Girdleness Road to its junction with Farquhar Road. There will be a prohibition of waiting on the same stretch of road. An alternative route is available via Girdleness Road, Balnagask Road, and Farquhar Road.

Phase 6; From 06:00 on 25 April 2022, until 06:00 on 27 May 2022, a Prohibition of driving on Farquhar Road, Aberdeen, from its junction with Farquhar Avenue to its junction with Rockall Road. There will be a prohibition of waiting on the same stretch of road. An alternative route is available via Balnagask Road.

Phase 7; From 06:00 on 8 July 2022, until 06:00 on 15 July 2022, a Prohibition of driving on Abbey Square, Aberdeen, at its junction with Balnagask Road. An alternative route is available via Abbey Place. Prohibition of driving on Farquhar Road, Aberdeen, at its junction with Balnagask Road. An alternative route is available via Farquhar Avenue. Prohibition of waiting on either side of Balnagask Road, Aberdeen, from its junction with Abbey Place to its junction with Finnan Brae.



Illegally parked vehicles will be removed at the owners expense.

The measures are necessary to protect public safety during heating duct installation works. Any queries regarding this restriction can be directed to Hatton Traffic Management on 01224 795399, or info@hattontraffic.co.uk